Aiming at the features of having multi-disturbance and real time scheduling
framework of molten iron dynamic scheduling system based on two-stage case-based reasoning(CBR) is proposed according to the indices of molten iron oriented iron-steel correspondence
such as time
mass
composition
temperature and so on.In terms of characteristic of various disturbance of production site
two-stage case library is classified.Key technology of molten iron dynamic scheduling system including case representation
case retrieving
case adaptation and case maintenance is discussed.And the satisfaction evaluation indices of dynamic scheduling are computed.The experimental results using a lot of practical production data show molten iron dynamic scheduling system has velocity on reasoning
higher stability and validity on results.The technical methods of two-stage case-based reasoning have wide application prospects.